5 Road Projects in The Woodlands Area to Watch in 2025

Exciting developments are on the horizon for The Woodlands area as several road projects are set to commence or continue in early 2025. Here’s a friendly and easy-to-understand overview of what’s happening on our roads:

Upcoming Projects

  1. I-45 Improvements

    • What’s Happening? A 1.6-mile stretch of I-45, from Shenandoah Park Drive to Highway 242, is scheduled for reconstruction.
    • When? Work is expected to start in the first quarter of 2025 and continue through the third quarter of 2028.
    • Cost: Approximately $42.63 million, funded 80% by federal funds and 20% by the state.
  2. Highway 242 Eastbound Flyover Construction

    • What’s Happening? A new flyover ramp will be built to connect northbound I-45 directly to eastbound Highway 242, aiming to improve traffic flow.
    • When? The project received the go-ahead on October 2, 2024, with an estimated completion date of September 15, 2026.
    • Cost: Around $19.1 million, funded by Montgomery County and federal funds.

Ongoing Projects

  1. Robinson Road Realignment

    • What’s Happening? Robinson Road is being realigned to create a direct crossing over Hanna Road, which includes adjustments to the Union Pacific Railroad crossing.
    • When? Construction began in February 2024, with an anticipated completion by April 2025.
    • Cost: Estimated at $7.42 million, funded by the city of Oak Ridge North.
  2. David Memorial Drive Extension

    • What’s Happening? David Memorial Drive is being extended to reach Highway 242, enhancing connectivity in the area.
    • When? Phase 1 started in September 2023 and is expected to conclude by March 2025. The timeline for Phase 2 is yet to be determined.
    • Cost: The total project is projected at $7.8 million, with funding from the city of Shenandoah and Montgomery County.
  3. Grogans Mill Road and Research Forest Drive Turn Lane Extension

    • What’s Happening? The deceleration lane from westbound Research Forest Drive onto northbound Grogans Mill Road is being extended to ease traffic congestion.
    • When? Work commenced in September 2024 and was initially expected to finish by late November 2024; however, delays have occurred due to utility relocations.
    • Cost: Approximately $240,000, funded by Montgomery County Precinct 2 and TxDOT.
  4. Highway 242 Widening

    • What’s Happening? Highway 242 is undergoing widening between FM 1488 and I-45, utilizing existing right of way to add lanes and restripe intersections.
    • When? The project began on October 23, 2023, and is slated for completion in the first quarter of 2026.
    • Cost: Estimated at $29.11 million, with funding from federal and state sources.

These projects aim to enhance traffic flow and safety in The Woodlands area. Stay tuned for further updates as construction progresses!