"It is unfortunate that the trees perished." Michael Robinson, a principal at SWA Group, the firm that designed the landscaping for the Montrose Boulevard rebuild, said it at the October 21 Montrose Redevelopment Authority meeting, as Community Impact reported. More than 30 trees on the new boulevard had died or struggled through the summer heat and were replaced.
The concrete on Montrose Boulevard between Allen Parkway and West Clay is essentially done. The Montrose TIRZ 27's next round of work moves off that arterial and onto the residential streets where the mature canopy actually is: Stanford, Columbus, Mandell, the Cherryhurst grid and, after those, West Alabama. On those blocks, the boulevard's lesson carries more weight. Once the crews leave, the trees still need years of watering before they're established.
The boulevard is down to rails, punch lists and watering
On paper the Segment 1 contract ran its course long ago. The engineer's pay estimate dated October 1, 2026 lists a substantial completion date of March 14, 2026, all 349 contract days used, and 97.53% of the work in place as of September 30. The contract total stands at $18,790,803.15, which includes an $894,800.15 change order approved in December 2025.
The TIRZ's October 2026 progress report lists what remains on the half-mile from Allen Parkway to just south of West Clay:
- Remaining punch list items, which can now be addressed because the bridge rail materials have arrived
- Landscape warranty work
- Tree replacement updates
The bridge in question is the pedestrian crossing over Allen Parkway, built in collaboration with Downtown TIRZ 3 to connect Montrose to Buffalo Bayou Park. The rest of the corridor is already in daily use: four 12-foot lanes in 11-inch concrete designed to last at least 50 years, an upgraded signal at West Dallas, a HAWK signal at West Clay, and City-owned Davit double-luminaire streetlights built to support METRO's BOOST 56 bus service. Beneath the roadway, 10-foot by 10-foot box culverts replace the old 48- and 54-inch pipes and hold roughly five acre-feet of stormwater.
What the replaced trees revealed
According to Community Impact's account of the October 21 meeting, Robinson said SWA's assessment found the trees had not been watered properly. Timing was a second factor. The project specifications call for planting between October 1 and February 28, and trees that go in later, as temperatures climb, have a harder time establishing.
The outlet also reported a mechanical detail. When crews watered from trucks with hoses, the force washed away the soil mounds built around each trunk to hold water, so less water reached the roots. The replacements now have Gator bags that are filled daily unless rain makes it unnecessary, along with watering tubes near the ground that deliver water to the roots and let workers check moisture.
The boulevard's watering period also runs four years, twice the two years such projects typically require, which Robinson attributed to the corridor's high profile. The contract prices it as a 48-month warranty and grow-in period at $8,000 a month, $384,000 in all, covering watering, mowing, stake removal, pruning and fertilizing. The plantings are live oaks to match the ones preserved along the road, plus Lanana cypress north of West Dallas, a species that came out of community engagement as a transition into Buffalo Bayou Park.
So the boulevard will keep getting regular attention until well after its ribbon-cutting photos are old. The work that decides whether this project succeeds now happens with a water truck, and it runs on the same October-to-February calendar the side-street projects are entering.
Where the work goes next
Each of the TIRZ's next projects runs through residential blocks, and each lists tree protection in its scope. Here's where they stood in the TIRZ's October 2026 progress report and draft schedule.
| Project | Where | Contractor | Status in October 2026 |
|---|---|---|---|
| Cherryhurst Sidewalks | Dunlavy, Fairview, Westheimer and Yupon | Ceballos Construction | Substantially complete since September 3, contractor working the punch list |
| Montrose Safe Routes to School Connections | Routes to Wharton Dual Language Academy, Carnegie Vanguard and Gregory-Lincoln | Precise Services, Inc. | Final City comments being addressed, notice to proceed after plan approval |
| Mandell Street Sidewalks | US-59 to Westheimer | JFT Construction | City routed plans for signature, notice to proceed after plan approval |
| West Alabama Reconstruction | South Shepherd to Spur 527 | Not yet bid | 75% plans submitted October 2, under City review |
Cherryhurst is the preview. New five-foot sidewalks, wheelchair ramps and driveways went in, usually on one side of each street.
Stanford, Columbus and the school routes
Safe Routes to School is the largest of the group. As Community Impact summarized it, it covers 4.5 miles of reconstructed and widened sidewalks for $8.9 million, funded by H-GAC and the TIRZ, and timed to start in late 2026. The TIRZ's draft schedule shows construction commencing in October or November 2026, lasting about a year, and reaching final completion in October or November 2027.
The project page lists the street-level changes:
- HAWK signals at Stanford and West Gray and at Stanford and West Dallas
- A mid-block crossing on Columbus Street by Wharton Dual Language Academy
- Pedestrian crossing signage at West Clay and Crocker
- Landscape changes at Stanford and Bomar to make pedestrians more visible at an intersection with a high historical crash rate
- Asphalt mill and overlay at five intersections to remove ADA barriers
- An individualized protection plan for each tree along the routes
The tree plan is the same commitment the boulevard is now paying to keep with daily Gator bags, written into the scope before the first sidewalk panel comes out.
Mandell, end to end
The Mandell Street Improvements project runs the full stretch from US-59 to Westheimer. It brings new five-foot sidewalks and ADA-compliant ramps, milling and overlay of the worn asphalt, restriping, new signage where needed, upgraded streetlights and its own tree protection plan. The board awarded the construction contract to JFT Construction at $1,205,428.60, plus a $308,768 HR Green contract for construction management, inspection and materials testing. The City-approved plan set posted on the TIRZ site is dated October 26, 2026.
West Alabama is the next boulevard-scale job
West Alabama is where the scale returns. The TIRZ's draft bond offering describes a full roadway reconstruction from South Shepherd to Spur 527, including utilities, drainage and sidewalks, at an expected $33,806,602, with $11,149,937 coming from grants. To cover part of that cost, the authority is planning $29,895,000 in Series 2026 tax increment contract revenue bonds and selected Hilltop Securities as underwriter.
The proposed street keeps one travel lane in each direction and adds a clearly marked center turn lane, left-turn lanes at key cross streets, new signals and six-foot sidewalks on both sides, replacing today's four- to five-foot walks. Storm sewers grow from 6 by 3 feet to as large as 6 by 6, with more than five acre-feet of detention. The design calls for planting new trees about 30 feet apart wherever possible. The engineer's October to-do list includes presenting the project objectives again with a focus on tree preservation and planting.
Montrose Boulevard isn't finished either. The same document describes Segment 2, from West Clay to US-59, as a planned continuation, with the authority expecting to spend $27,585,000 on it. On the stretch from West Clay to Westheimer, a separate City of Houston Public Works project is handling resurfacing, ADA ramps, spot sidewalk repairs and storm inlet upgrades, and the TIRZ directs questions about it to 311.
Keeping track from your own block
The TIRZ board meets on the third Monday of each month and posts its board books, which include the engineer's monthly progress report, on montrosehtx.org. The authority takes project feedback by email at [email protected]. The engineer is also wrapping up a streetlight audit of the zone, with next steps aimed at fixing the lighting gaps it found.
For anyone living along Stanford, Mandell or West Alabama, the date to watch is the notice to proceed, since that's when crews arrive. The trees planted on the boulevard this fall, and the ones the side-street projects are protecting, run on a longer schedule: the boulevard's grow-in contract keeps the watering going through four summers.